Main Activities |
Finish Date |
Start Date |
Eng. Man Hours |
Client |
Project Title |
No. |
|
Engineering ,blades supply, erection & unit commissioning Services |
06/1996 |
01/1996 |
1500 M.H Engineering + 154,000,000 RLs. Procurement |
(NIOEC) |
Bandar Abbas Refinery 450 m3/day VC type water Desalination plant (EPC) “2001” |
1 |
5-5- Backgrounds and Experiences in Drinking Water Transfer Lines, Storage and Treatment B) Completed Projects |
Project Construction Management |
11/1996 |
02/1995 |
~ 11000 |
Kish Water & Power Company (KWPC) |
Almahdi 1800 m3/day MED type Water Desalination “Bandar Abbas” (MC) “1001” |
2 |
|
Engineering, erection & commissioning services for 2 units |
01/1997 |
10/1996 |
~ 3000 |
(N.I.O.R. D.C.) |
Bandar Abbas Refinery 2×450 m3/day VC type water Desalination Plant “2002” |
3 |
|
Engineering, Erection & Commissioning Services for 2 units |
09/1997 |
5/1997 |
~ 3600 |
(N.I.O.R. D.C.) |
Bandar Abbas Refinery 2×450 m3/day VC Type Water Desalination Renovation “2006” |
4 |
|
Heat exchangers design |
12/1997 |
10/1996 |
~ 1000 |
Kish Water & Power Company (KWPC) |
Water Temp. Reduction System for Water desalination “ Kish Island “ “1007” |
5 |
|
Design & construction |
01/1998 |
07/1997 |
~ 2500 M.H+ 377,000,000 Rls Supply & Construction |
Almahdi Aluminum Complex |
Almahdi Desalination Sea Water Intake Structure “Bandar Abbas” (EPC) “2004” |
6 |
|
Technical review of water transfer line for operation with one or two pump sets. |
03/1999 |
03/1999 |
~ 500 |
Yazd Regional Water Co. |
Water Transfer From Zayanderood to Yazd “Yazd” “3005” |
7 |
5-5- Backgrounds and Experiences in Drinking Water Transfer Lines, Storage and Treatment B) Completed Projects |
Basic design and detailed Engineering of raw water pool and water supply pump station building |
11/2000 |
02/1999 |
~ 2500 |
(NIPEC) |
Meydook Cupper Concentrate Complex “Chahbahar” “4002” |
8 |
|
Basic and detail engineering and construction supervision. |
09/2001 |
05/2000 |
~ 35000 |
Sistan & Baluchestan Regional Water Co. |
2×15000 m3/day MSF type water Desalination “Chahbahar” “3006” |
9 |
|
Design and project Management. |
03/2002 |
10/1995 |
~ 36000 |
Kish Water & Power Co. (KWPC) |
Lavan Refinery 2×1800 m3/day MED type water desalination Lavan Island “Lavan Island” (MC) “1004” |
10 |
|
Feasibility study for water desalination plant in Hormozgan Power Plant |
08/2006 |
08/2005 |
~2000 |
Tavanir |
Hormozgan Desalination Plant
“6100” |
11 |
|
Feasibility and Marketing Studies for water Production In South provinces of Iran |
03/2011 |
12/2009 |
~ 3000 |
Iran Power Plats projects Management (MAPNA) |
Technical and Economical studies for water Production
“6183” |
12 |