Main Activities |
Finish Date |
Start Date |
Eng. Man Hours |
Client |
Project Title |
No. |
|
HVAC detail design for industrial buildings | 06/2003 | 08/2002 | ~3000 | Petrofac Iran Co. |
Dorood Onshore Facilities Development "Khark Island" “6041” |
1 |
5-3- Backgrounds and Experiences in Upstream and Surface Installations B) Completed Projects: |
HVAC detail design for non-technical buildings | 02/2004 | 01/2002 | ~5300 | Jahan Pars Eng. & Const. Co. |
Dorood Onshore Facilities Development "Khark Island" “6033” |
2 | |
Data collection, technical inspection, optimization studies and provision of EPC contract documents in cooperation with Canadian SNC Lavan Co. |
09/2004 | 09/2002 |
~50000 (Iranian Expertise) |
National Iranian South oil Company (NISOC) |
Production Optimization & Surface Facilities Renovation (POSFR) Maroon, Aghajari, Gachsaran, Ahwaz Field Areas. “6018” |
3 | |
Conceptual study, basic engineering design and provision of EPC contract package |
03/2006 | 08/2003 | ~16550 |
Iran Central Oil Field Co. (ICOFC) |
Naft Shahr Oil Field New Production Unit , Desalination and Gas Compressor Booster Station unit “6054” |
4 | |
Design, Procurement, Construction for Modernize Metering System for Khozestan Oil Pipeline EPC Contract |
06/2006 | 06/2004 |
15000 M.H + 2,200,000 $ Procurement & Construction |
National Iranian South oil Company (NISOC) |
Accurate Flow Metering System in production & distribution Areas (EPC) “6075” |
5 | |
Basic engineering studies and preparing 19 separate package tender documents for Renovation control system for about 97 different units (production and desalination units, NGL, Gas Compressor …) in south oil field and design SCADA system all in cooperation with a foreign partner(Tebodin Co.) |
02/2009 | 08/2006 | 121500M.H + $475,000 |
National Iranian South oil Company (NISOC) |
Instrumentation and Control Modernization and Establishment of Advanced Central Control System “6117” |
6 |