  No. Project Title
Client
Eng. Man Hours
Start Date
Finish Date
Percent Completion
Main Activities

5-2- Backgrounds and Experiences in Oil & Gas Transfer Pipelines

A) Current Projects

1

Imam Taghi/ Torbat Heidarieh Increasing Capacity of Oil Products Transfer

“6104”

(NIOEC)

15450 M.M +102 M.M Site

Supervision

11/2005

12/2012

~ 99.5 %

Design, procurement and

construction site supervision

Hirbodan Co. (MC contract)

2

Gas Compressor Stations For 6th Gas

Pipeline –IGAT6 Project

“6131”

Iran Gas Engineering and Development Company

~32000

06/2007

11/2011

Engineering activities 100%

Total progress

~45%

Basic Design ,EPC Tender Document Preparation ,Co-operation in Contractor Selection and EPC supervision

3

Basic Design of 16″ pipeline of Ray –Eshtehard

“6184”

Iran Pipeline & Communication Company

~18000

10/2009

02/2012

~98%

Basic Design of 16″ Product pipeline of Ray –Eshtehard & 12″ Product Pipeline Branch from main line to parand & RoodeShur Power Plant